USD 482 Construction Updates/ Schedule/Photo Album

Phase 1 HS

  1. December 6- remodel science rooms (206, 206A, 208)
  2. December 6- remodel FACS room (140)
  3. December 6- remodel research room (131) and corridor (105A)
  4. December 6- remodel elevator area to go in 1st and 2nd floors
  5. December 9-14- paint gym
  6. December 20-15- bleacher install in new gym
  7. December 22-January 4- hallway ceiling replacement 

Phase 2 HS

  1. Feb 2- remodel north science room
  2. Feb 2- remodel of east FACS room
  3. Feb 2- remodel teachers lounge 130
  4. Feb 22 to May 8- remodel concession stand (112A)
  5. Feb 22 to May 8- remodel restrooms (115A, 115B)

HS Summerwork

  1. Remodel restroom (110A)
  2. Remodel restroom (105B,105C)
  3. Remodel restroom (212)
  4. Remodel main office and corridor (100)
  5. Remodel auditorium from April to July
  6. Exterior concrete and entry doors

Phase 1 GS

  1. December 13- remodel north locker room 
  2. December 22- Jan 14- install clouds in classroom 
  3. Feb 9- remodel south locker rooms
  4. March 16- 22- replace library ceilings 

GS Summerwork

  1. Main office area
  2. corridor (100)
  3. lobby (101) 
  4. hallways